Lamthap factory – Boiler Modification

The existing 30 T-steam/hr water tube boiler at Lamthap factory has been modified and upgraded from saturated steam output to superheated steam output. The superheated steam has greater internal energy that can be used to power a new high efficiency steam turbine, to be installed in 2023. This modification allows us to reduce the fuel intake and produce significantly more power to run our own operation, in particular our kernel crushing plant.

 

Currently we use our own biogas produced power and also the local grid to run our kernel crushing operation. We will be able to reduce significant power costs and supply the local grid with more of our biogas produced power.